top of page
Search

Two Months to One Week: The Power of Precast Value Engineering.

Writer: Kathy Zonyk
Kathy Zonyk
11 minutes ago
3 min read

In heavy civil construction, deep excavation projects carry major risks, including long

schedules, heavy labor demands, traffic disruptions, and unpredictable site conditions.

When Earle Asphalt Company took on a complex project requiring a large manhole

chamber, a dual culvert run, and retaining walls, the original plans specified traditional

cast-in-place (CIP) concrete.


Recognizing the risks of building deep within a cofferdam on a busy corridor, Garden State

Precast value-engineered the design. Converting the field-built structures into a complete

precast package slashed an estimated two-month installation down to one week, removed

major safety hazards, and delivered substantial cost savings to the owner.




The Power of a 3-in-1 Unified System

Consolidation drove the project's success. Already contracted to supply the precast box

culvert, Garden State Precast’s engineering team analyzed the blueprints and proposed

converting the CIP manhole chamber and poured walls into modular precast components,

using interlocking Stone Strong blocks for the retaining walls.


This redesign created a coordinated, 3-in-1 single-supplier package from inlet to outlet.

Instead of aligning field-poured concrete to precast pipes in the trench, one manufacturing

team designed and fabricated every piece. This unified approach gave crews complete

certainty over structural connections, delivery schedules, and installation tolerances

before equipment even reached the site.


The Customer’s Perspective: Operational Control and Execution

Pivoting away from the original cast-in-place plans eliminated the unpredictable field

variables that typically delay major utility work.


"Going precast on the manhole chamber and inlet/outlet walls instead of the cast-in-place design shown on the plans turned out to be one of the best decisions we made on this project," says Ryder Grimes with Earle Asphalt Company. "Rather than matching field-built structures to precast sections, every piece was designed, fabricated, and delivered by the same team. This gave us better control and certainty over the whole install, from how the connections lined up to how deliveries and setting were sequenced."

Engineering Out the Risk: Preplanning and Prototyping

To ensure smooth execution, Garden State Precast joined Earle’s preplanning phase using

a 3D-printed physical model of the chamber and wall connections. This hands-on

prototype allowed engineers, project managers, and field superintendents from both

teams to inspect interfaces, verify connection points, and map out the crane-setting

sequence. Identifying and resolving alignment conflicts in the o ice prevented costly

delays during live excavation.


Compressing Months into Days

Traditional cast-in-place construction creates a slow, sequential bottleneck involving

formwork setup, rebar tying, concrete pours, curing time, and form stripping. Earle’s team

estimated that building this structure in the field would take anywhere from several weeks

to two months.


Precast concrete compressed this timeline by enabling concurrent workflows. While

Earle’s crews handled site prep, earthwork, and foundation stabilization, Garden State

Precast fabricated the structural components offsite. Once the excavation was ready,

cured pieces arrived on-site for immediate placement. Crews installed the entire precast

chamber in 6 hours and completed the full system in about one week.


Unlocking Safer Jobsites and Efficient Manpower

Beyond speed, precast delivered major safety improvements. A cast-in-place build would

have kept workers inside a deep, confined cofferdam pit for weeks, exposed to heights,

tight spaces, and heavy formwork bracing. Precast engineered these hazards out of the

jobsite:

  • Reduced Hazard Exposure: Crew time inside the deep excavation dropped from months to a few days.

  • Safer Work Environments: On site fabrication eliminated tying rebar and building

    forms at high elevations inside the pit.

  • Decreased Site Congestion: Crane-setting operations required fewer workers in

    the trench, reducing overcrowding.


Additionally, shifting fabrication to a precast plant freed up Earle’s specialty concrete crew

during the peak summer construction season, allowing them to focus on other critical

project milestones.



Protecting the Traveling Public

The jobsite sat along a high-volume summer route leading to the Jersey Shore, where long-

term traffic shifts increase driver frustration and work-zone accident risks. Because

precast installation moved so quickly, Earle dramatically shortened the tra ic shift.

Restoring normal traffic flow weeks ahead of schedule eased regional congestion and

protected both drivers and roadside crews.


The Plant-Controlled Quality Advantage

Precast manufacturing also upgraded the structure's long-term quality. Unlike field

concrete—which is vulnerable to shifting weather, temperatures, and delivery delays—

precast components are produced in a strictly monitored, climate-controlled plant.

This controlled setting guarantees accurate batching, proper consolidation, and ideal

curing temperatures, producing higher initial concrete strength and lower permeability.

Technicians inspect rebar placement, clearances, and embedded hardware before

pouring, achieving dimensional precision and durability that field-poured concrete cannot

match.


Conclusion: A Blueprint for Cost and Schedule Certainty

Large cast-in-place structures carry heavy financial risks from labor overruns, material

waste, curing delays, and bad weather. Precast concrete removes these variables by

locking in scope and material pricing upfront. By choosing a value-engineered precast

solution, Earle Asphalt Company and Garden State Precast delivered a superior, durable

system ahead of schedule, under budget, and with far lower safety risks—passing

measurable savings directly to the project owner.




 
 
 

Recent Posts

See All

Comments


GSP-LogoPMS340.png
NPCA_prog-RGB_member.png
NPCA_prog-RGB_certplant.png
EssentialManufacturer.png

Head Office

1630 Wyckoff Road
Wall, NJ, 07719


Mailing Address:

PO Box 702
Farmingdale NJ 07727

Phone: 732-938-4436
Fax: 732-938-7096
sales@gardenstateprecast.com

​

​​

​

PRICE LIST

​

​

Serving

Serving New Jersey, Pennsylvania, New York and Delaware for over 25 Years!

​

Garden State Precast is an Approved Supplier of NJDOT, DELDOT, NYCDDC, PANYNJ,
PENNDOT, and PSEG

Socials

FB.jpeg
icons8-linkedin-48.png
inst.jpeg

© 2026  Garden State Precast All Rights Reserved

bottom of page