Two Months to One Week: The Power of Precast Value Engineering.
In heavy civil construction, deep excavation projects carry major risks, including long
schedules, heavy labor demands, traffic disruptions, and unpredictable site conditions.
When Earle Asphalt Company took on a complex project requiring a large manhole
chamber, a dual culvert run, and retaining walls, the original plans specified traditional
cast-in-place (CIP) concrete.
Recognizing the risks of building deep within a cofferdam on a busy corridor, Garden State
Precast value-engineered the design. Converting the field-built structures into a complete
precast package slashed an estimated two-month installation down to one week, removed
major safety hazards, and delivered substantial cost savings to the owner.

The Power of a 3-in-1 Unified System
Consolidation drove the project's success. Already contracted to supply the precast box
culvert, Garden State Precast’s engineering team analyzed the blueprints and proposed
converting the CIP manhole chamber and poured walls into modular precast components,
using interlocking Stone Strong blocks for the retaining walls.
This redesign created a coordinated, 3-in-1 single-supplier package from inlet to outlet.
Instead of aligning field-poured concrete to precast pipes in the trench, one manufacturing
team designed and fabricated every piece. This unified approach gave crews complete
certainty over structural connections, delivery schedules, and installation tolerances
before equipment even reached the site.
The Customer’s Perspective: Operational Control and Execution
Pivoting away from the original cast-in-place plans eliminated the unpredictable field
variables that typically delay major utility work.
"Going precast on the manhole chamber and inlet/outlet walls instead of the cast-in-place design shown on the plans turned out to be one of the best decisions we made on this project," says Ryder Grimes with Earle Asphalt Company. "Rather than matching field-built structures to precast sections, every piece was designed, fabricated, and delivered by the same team. This gave us better control and certainty over the whole install, from how the connections lined up to how deliveries and setting were sequenced."
Engineering Out the Risk: Preplanning and Prototyping
To ensure smooth execution, Garden State Precast joined Earle’s preplanning phase using
a 3D-printed physical model of the chamber and wall connections. This hands-on
prototype allowed engineers, project managers, and field superintendents from both
teams to inspect interfaces, verify connection points, and map out the crane-setting
sequence. Identifying and resolving alignment conflicts in the o ice prevented costly
delays during live excavation.
Compressing Months into Days
Traditional cast-in-place construction creates a slow, sequential bottleneck involving
formwork setup, rebar tying, concrete pours, curing time, and form stripping. Earle’s team
estimated that building this structure in the field would take anywhere from several weeks
to two months.
Precast concrete compressed this timeline by enabling concurrent workflows. While
Earle’s crews handled site prep, earthwork, and foundation stabilization, Garden State
Precast fabricated the structural components offsite. Once the excavation was ready,
cured pieces arrived on-site for immediate placement. Crews installed the entire precast
chamber in 6 hours and completed the full system in about one week.

Unlocking Safer Jobsites and Efficient Manpower
Beyond speed, precast delivered major safety improvements. A cast-in-place build would
have kept workers inside a deep, confined cofferdam pit for weeks, exposed to heights,
tight spaces, and heavy formwork bracing. Precast engineered these hazards out of the
jobsite:
Reduced Hazard Exposure: Crew time inside the deep excavation dropped from months to a few days.
Safer Work Environments: On site fabrication eliminated tying rebar and building
forms at high elevations inside the pit.
Decreased Site Congestion: Crane-setting operations required fewer workers in
the trench, reducing overcrowding.
Additionally, shifting fabrication to a precast plant freed up Earle’s specialty concrete crew
during the peak summer construction season, allowing them to focus on other critical
project milestones.

Protecting the Traveling Public
The jobsite sat along a high-volume summer route leading to the Jersey Shore, where long-
term traffic shifts increase driver frustration and work-zone accident risks. Because
precast installation moved so quickly, Earle dramatically shortened the tra ic shift.
Restoring normal traffic flow weeks ahead of schedule eased regional congestion and
protected both drivers and roadside crews.
The Plant-Controlled Quality Advantage
Precast manufacturing also upgraded the structure's long-term quality. Unlike field
concrete—which is vulnerable to shifting weather, temperatures, and delivery delays—
precast components are produced in a strictly monitored, climate-controlled plant.
This controlled setting guarantees accurate batching, proper consolidation, and ideal
curing temperatures, producing higher initial concrete strength and lower permeability.
Technicians inspect rebar placement, clearances, and embedded hardware before
pouring, achieving dimensional precision and durability that field-poured concrete cannot
match.
Conclusion: A Blueprint for Cost and Schedule Certainty
Large cast-in-place structures carry heavy financial risks from labor overruns, material
waste, curing delays, and bad weather. Precast concrete removes these variables by
locking in scope and material pricing upfront. By choosing a value-engineered precast
solution, Earle Asphalt Company and Garden State Precast delivered a superior, durable
system ahead of schedule, under budget, and with far lower safety risks—passing
measurable savings directly to the project owner.