Route 206 Crusers Brook Bridge Project


Garden State Precast Project #: 17-42643

Project Name: NJ ROUTE 206 CRUSERS BROOK BRIDGE DP 17102

Location: HILLSBOROUGH TWP NJ

Project start date: NOVEMBER 2018

Project end date: SPRING 2019

Synopsis of Development:

This is a design-build project that Garden State Precast participated in during a four-year period. The project consisted of twenty-four, large, three-sided frames in a dual run configuration. GSP was involved in the design, production and shipment of the units.

Design Challenges and Project Constraints:

This project was designed and deployed over a four-year period. Challenges included project geometry, barrier HL4 ratings, phase construction, special high-strength concrete, shipment to project site, rigging and handling for a 90 degree roll from form to shipment then another 90 degree roll from shipment to installation. All units also required manufacturing on a 30 degree skew.

Fabrication and Testing Activities:

  • Design, purchase of specific formwork, and production of (24) 33’ x 11’-2 frames
  • Validation on NJDOT Class P2 concrete – 6500 psi.

Precast Concrete Bridge Project

Precast Concrete Bridge Project

Precast Concrete Bridge Project

Precast Concrete Bridge Project

NPCAADSStone Strong Effluent Design Alp SupplyJersey Specialized  

Garden State Precast
1630 Wyckoff Road
Wall, NJ, 07719
Mailing Address:
PO Box 702, Farmingdale NJ 07727
Phone: 732-938-4436
Fax: 732-938-7096

Email: info@gardenstateprecast.com

Serving New Jersey, Pennsylvania, New York and Delaware for more than 20 Years!

Garden State Precast is an Approved Supplier of NJDOT, DELDOT, NYCDDC, PANYNJ,
PENNDOT, and PSEG

Copyright © 2019-2020
Garden State Precast
All Rights Reserved
Essential NJ Manufacturer